The progress of the construction of greenhouse complex “Martynovskiy”

The company “PKF AGROTIP” continues the construction of the greenhouse complex “Martynovsky” in the village of Martynovka in the Kurgan region. By the October 2018 70 % of the structures have been installed, 50% of the irrigation water supply to the complex is ready. The roof installation is in full progress. The power center is in the final stage of the construction.

Watch the video from the construction of the facility.

 

Photos from the construction site.

 